Exeter
Exeter, Rockingham County , Project 130-18
Infrastructure (Construction) Wastewater
What the funding was for
The funding recipient used the funding to design and construct an additional sewage siphon barrel to improve the capacity of existing sewage siphon located under the Squamscott River.
Project description provided by NHDES.
How it was funded
$5,280,000 committed on January 22, 2021
Two funding sources combined — CWSRF and ARPA — for a total commitment of $5,280,000.
- CWSRF $5,100,000 (97%)Clean Water State Revolving Fund (CWSRF)
- ARPA $180,000 (3%)American Rescue Plan Act (ARPA)
Location
Shown at the center of Exeter, not at the exact project site.
Where this fits: Rockingham County’s funding timeline
Between January 2021 and July 2026, NHDES committed $8,180,000 to 2 projects in Rockingham County. The largest single commitment was $5,280,000 to Exeter in 2021.
Jan 22, 2021
Exeter
Infrastructure (Construction)
$5,280,000 to design and construct an additional sewage siphon barrel to improve the capacity of existing sewage siphon located under the…
- Earliest ARPA-funded
- Earliest CWSRF-funded
- Largest commitment
Jul 29, 2026
Newfields Water & Sewer
Newfields
$2,900,000 to test well exploration, install new production well(s) and design, permit and construct necessary facilities to accommodate the…
- Earliest DWSRF-funded
Other projects nearby
Newfields Water & Sewer
Newfields, about 3 miles away
Infrastructure (Construction) Drinking Water
$2,900,000 committed
Dover
Dover, about 14 miles away
Planning Stormwater
$100,000 committed
Lee Oak Cooperative, Inc.
Barrington, about 16 miles away
Infrastructure (Construction) Drinking Water
$430,000 committed
Allenstown
Allenstown, about 24 miles away
Infrastructure (Construction) Wastewater
$225,000 committed
Distances are between town centers.